A Project Manager of a Chinese Civil Engineering and Construction
Company, Etim Abak has told the Senate Committee on the Federal Capital
Territory how former President Olusegun Obasanjo awarded the Abuja Rail
Project in 2007 without an engineering design or a Memorandum of
Understanding and inflated the rail project by $10m per km.
The revelation was made when the Senate Committee on Federal
Capital Territory (FCT) led by Dino Melaye visited the site of the
project to carry out oversight functions, Punch reports.
The committee discovered that the former Minister of FCT and
current governor of Kaduna State, Mallam Nasir el-Rufai, allegedly
signed the $841.645,898m contract based on an uncalculated estimate.
The committee also discovered that the contract, which was for
60.67-kilometre rail project, was inflated by $10m per km and that the
length was later reduced to 45km without refund of the cost for the
15.67 km. All these were done against the laid down rules and regulation
for which contracts are to be awarded.
In the face of that, the senate committee ordered the company to
immediately refund $195,878,296.74 being the amount for the 15.67km that
was cut out for cheating Nigerians.
Abak said, “The contract was awarded based on conceptual design
and estimates were not properly done. There was no formal design
submitted and rail bridges and crossover bridges were not captured in
the contract.”
However, Melaye said his findings revealed that the rail project
was inflated by over $10m per km and expressed his disgust at the
conduct of the company to shortchange Nigerians.
“Now, you have reduced the length of the kilometre standard
gauge from 60.67 kilometres to 45.245 kilometres. Meanwhile, there is no
concomitant reduction if you juxtapose the length of kilometres and the
reduction in terms of the cost.
“If we are to spend $841 million for 60.67 kilometres and now
you have reduced to 45.245 kilometres and the only reduction in terms of
monetary value is from $841.6 million to $823 million and with
reduction of just about $17 million that to me is not commensurate to
the reduction in terms of length, ‘’ he said.
He added: ‘’The federal government has so far invested $31.5
billion and another $7.6 billion from the SURE-P fund and if you put
these together, we have altogether $39.1 billion invested in the rail
project, leaving the balance of $113. 233 million. The sum of $3 million
was proposed in the 2016 national budget of the FCT for the rail
project.
“If you look at this, I would want to say that I did a personal
research and looked at rail construction of the same specifics, of the
same technology across the globe and one cannot but complain that this
railway project in Nigeria is on a very high side.”
The committee also questioned the rationale behind obtaining $500
million from Exim Bank of China for the project by the federal
government, arguing that the money already injected into the project was
more than enough to complete the project. Melaye insisted that the
contract was inflated.
‘’From our research and it’s very simple, the world is now a
global village. As you are sitting here now, on your phone, you can
google even in India and Egypt. Fortunately, one of those projects in
Zambia was also done by this same company, CCE.
“We have six countries and the average cost per kilometre, none
is $4 million per kilometre. Why is the Nigerian project costing $13.8
million approximately $14 million dollars per kilometre.”
No comments:
Post a Comment